Streets · July 13, 2026
Construction on the Lincoln Avenue / 16th Street storm sewer project moved forward through the summer. At its June 8, 2026 meeting, Council approved the project’s first application for payment to Mitchell Contracting — $93,824.64, reviewed by P. Joseph Lehman Engineering and Highway Superintendent Eric Desch.
At the July 13 meeting, Council approved Change Order No. 1 in the amount of $15,982.59, covering additional work required by the elevation of a drainpipe exposed on Lincoln Avenue, along with a further payment of $43,018.55 to Crystal L. Mitchell Excavating.
The project is supported in part by the Borough’s 2026 CDBG funds — see Resolution 2026-06.
Approved unanimously
Each item was approved unanimously by the members present at the June 8 and July 13, 2026 meetings.