Adopted by Borough Council · February 9, 2026
Council on February 9, 2026 adopted Ordinance No. 1496, replacing the rules that govern how a street must be put back together after a contractor cuts into it. The previous ordinance dated to 1988 and had grown significantly out of date. The new version brings Tyrone’s requirements in line with current state law and current practice in the region, and it leans on a stricter standard for the larger jobs that leave a street patched edge to edge.
Adopted unanimously
In favor: all members present — Robert Dollar, Sarah Hunter, Ken Patterson, Bridgette Gill, Tammy Wills, William Wiser, Mayor Harlow.
Whenever a utility, a developer, or a contractor opens a Borough street — to reach a water or sewer line, set a new service, or run a connection — the trench has to be filled and the surface restored. Restoration standards exist because a poorly patched cut becomes tomorrow’s pothole: water seeps into the seam, the subbase shifts, and the patch fails while the rest of the road is still sound. The Borough, not the contractor, is usually left maintaining the result for years afterward.
New state legislation gives municipalities broader authority to require more substantial repair from the contractors who do this work. The 1988 ordinance predated that authority, so Council’s update is partly a matter of catching the Borough’s own code up to what the law now allows it to demand. In drafting the revisions, staff modeled the requirements on the standards the City of Altoona currently uses.
The most consequential change sets a threshold tied to how much of a street a project disturbs. Under Ordinance No. 1496, a contractor whose work affects more than fifty percent of a Borough street must restore the entire street — not just the trench line or the lane that was opened. The reasoning is straightforward: once a job has torn up more than half the pavement, a series of patches leaves the road weaker and shorter-lived than a full, uniform resurfacing would, and the seams between old and new pavement are exactly where roads begin to come apart.
For residents, the effect is on the condition of the streets rather than anything you need to do. The cost of the more extensive restoration falls on the contractor performing the work, and the standard is meant to ensure that a street reopened after a major project is left in sound, finished condition rather than as a quilt of patches. Anyone planning to excavate in a Borough street should review the current restoration requirements before scheduling work.
Read the law: street excavation and restoration are governed by Chapter 172, Streets & Sidewalks of the Tyrone Borough Code, online at ecode360.com/TY1357.